Reconstruction and replacement of technological devices of the Main Sewage Pumping Station in Mrągowo.

GENERAL INFORMATION

Location: Mrągowo

Ordering Company : Public Utility Project for Mrągowo

Date: 2018/2019

PROJECT DESCRIPTION 

On June 12, 2019, the contract was completed by the Technological Execution Department of Ecol-Serwis: Reconstruction and replacement of technological devices of the Main Sewage Pumping Station in Mrągowo.

The value of the investment, which lasted about 1 year, is  5 457 404 PLN. The contract was carried out by the Technological Execution Department of the Ecol-Serwis Division.

The investment of reconstruction of the pumping station was implemented by the Mrągowo Commune with the participation of EU funds under the project: “Modernization and expansion of sewage and water supply systems of the Mrągowo agglomeration under measure 2.3” Water and sewage management in agglomerations “priority axis II” Environmental protection, including adaptation to climate change “Operational Program Infrastructure and Environment 2014 – 2020.”

 

As part of the task, works related to the assembly of modern technological, electrical and I&C installations were completed. The works also included the delivery and assembly of pumps with a capacity of Q = 450 m3 / h and a power of P = 75 kW and pipelines made of AISI 316L steel, construction of a ventilation and heating system based on heating and ventilation units. A video monitoring system with an alarm system and data transmission was also installed. The pumping station serves the entire city of Mrągowo, therefore all works were carried out with the uninterrupted operation of the pumping station using emergency systems. All technological and sanitary works were carried out without the participation of subcontractors. Installation capacity H = 125 l / s, H = 56 m.

GALERY